Anti termite treatment is carried out in four stages described below.

One (1) Stage


  1. Floor Slab
    This treatment is applied on the prepared, compacted hardcore, i.e on the underside of the floor slab with concentration of spray on both sides/edges of the ground beams. This constitutes the first stage of the treatment.

Two (2) Stage
 

  1. Floor Slab
    The treatment is applied on the prepared, compacted hardcore, i.e. on the underside of the floor slab with concentration of spray on both sides/ edges of the ground beams. This constitutes the first (1st) stage of the treatment.

     
  2. Apron
    During the second stage, anti- termite solution is applied on the prepared hardcore at the apron area, porch, patio, lanai and other covered areas.

Three (3) Stage

  1. Foundation and Ground Beams
    Anti treatment is applied on the foundation and ground beams with concentration on both sides/edges of the ground beams.

     
  2. Floor Slab
    Anti termite treatment is applied on the prepared, compacted hardcore

     
  3. Apron
    Anti termite treatment is carried out on the prepared hardcore at the apron area.

Four (4) Stage

  1. Foundation
    When piling is completed, we carry out the anti termite treatment into the soil at the foundations.

     
  2. Ground Beams
    After the pile caps are erected, the anti termite treatment is carried out at the ground beams.

     
  3. Floor Slab
    The anti termite treatment is applied on the prepared compacted hardcore floor slab.

     
  4. Apron
    Anti termite treatment is carried out on the prepared hardcore at the apron area.